| |||||
2003 Project Status ReportWest Parking Lot Reconfiguration--COMPLETE
In response to comments received in our Customer Satisfaction Survey and to aid snow removal efforts, Law General Contracting reconfiguring a portion of the west parking lot, the busiest lot on the COATC campus. The project involves realignment of roadway, removal of several islands, and creation of a buffer adjacent to the Conference Center in preparation for a major repaving project which is slated for Summer 2004.
Monitoring System--COMPLETE
Kemper Controls has completed initial testing with final ramp up expected in early 2004 on a five-station wireless monitoring system. The system, which connects to the newly-installed wireless network, upgraded alerts on five critical utility systems from flashing-light alarms to actual monitoring and remote alert systems. The system provides alert functions via the web and telecommunications devices while also allowing for more detailed monitoring. In the near future, the Port Authority will be able to monitor, via the Internet, the status of these critical systems around the clock.
Wireless Network--COMPLETE
Parellel Technologies engineered and installed a wireless network to connect existing and future wireless components to the Port Authority's network server. The network gives direct server access for information sharing and sharing of Internet service at facilities outside of the Port Authority's administration building.
Building 4 Roof Repair--COMPLETEA repair project for a major roof section for Building 4 is now complete. Equipment was hoisted onto the roof by crane on September 2nd. The project was completed three weeks ahead of schedule, within budget, and with no substantial change orders. The repairs were to a section repaired in 2001, never properly completed, and found to be unsatisfactory. Kalkreuth Roofing & Sheet Metal, Inc. was awarded the contract July 15 after a public bid.
Rec Center Gutter Drains--COMPLETEIn August, Layton Excavating completed a project designed to divert waterflow so as to prevent ice build-up in the street between Buildings 2 and 4.
Improvements to Upper Walkway--COMPLETEVillage Landscaping completed landscaping updates at the start of this project to make room for lighting changes. ARC Electrical Contractors is now complete with installation of a bollard lighting system. This project was designed to improve access to the upper parking lot while easing maintenance and snow removal.
Exterior Painting Projects--COMPLETE![]()
Painting is complete on several leased buildings on the Base campus, including Building 20 which is leased to BAE SYSTEMS and Building 56 which is leased to Boeing for fire department operations. Lacey Painting was the contractor.
Exterior Painting Projects--COMPLETEPainting is complete on Building 17 which houses the Port Authority equipment fleet.
Masonry and Concrete Repairs--COMPLETEWork was completed in late May for storm sewer and building items in need of mortar and concrete repair at four locations on the main campus. Kel-Par Company of Newark was the contractor.
Guard Rail Post Replacement--COMPLETEA&B Fencing was contracted to replace damaged guard rail posts at various locations, particularly the western entrance to COATC.
Conference Center Roof Repair--COMPLETEEmergency repairs were made in late April to the roof overhang over the west side of the conference center. The roof sections received minor damage by being struck by a truck and, upon investigation, were found to have more significant damage. Claggett and Sons of Newark completed repairs May 2nd.
Conference Center Modernization--COMPLETEModernization of the COATC Conference Center is now complete. The modernization increased usable floor space, improved lighting and sound, and transformed the facility into a more multi-purpose facility. The conference and meeting room facility is adjacent to Aramark's Flightline Cafe. It was known as the Consolidated Open Mess (C.O.M.) during the Air Force days and had not seen a major renovation since 1973. See the 360° view of the modernization project as of February 14, 2003.
BAE SYSTEMS Building Renovation--COMPLETERenovation of the office portion of Building 20, occupied by BAE SYSTEMS, is now complete. Work was completed January 10. The renovations included ceiling, flooring, and other minor interior improvements designed to provide a more modern office setting. BAE SYSTEMS leases the space under a lease with the Port Authority begun in November 2002. The renovations were tenant-funded with the contracts managed by the Port Authority.
Meeting Rooms--COMPLETETwo rooms at the West side of the COATC Conference Center and totalling 729 sq. ft. have been reconfigured for use as meeting rooms. Work was completed in January. One room makes an excellent small conference room. The larger room holds up to 32 people for seminars and training sessions and more for receptions.
See the archive of projects completed in 2002.
Make An Inquiry to The Facilities Manager
Have a question or comment about a project? Contact our Facilities Manager.